Projects by sector, with the responsibilities held, the project value and the year.

Clients

  • Balfour Beatty Construction
  • Barratt E+M
  • Courtcraft
  • Galliford Try Construction
  • Graham Construction
  • GW North West
  • ISG Construction
  • ISG Retail
  • JamesQS Ltd
  • Kier Construction Ltd
  • SPL Electrical
  • ST1 Consulting
  • Stewart Milne Homes
  • Thomas Vale Construction (Strategic Projects)
  • Tolent Construction
  • Wates Construction Ltd

Education

SectorLocationResponsibilitiesValueYear
University BuildingNorth WalesEngaged by Main Contractor to assist in building up variations in relation to the preparation of the final account on a new £35m build project in North Wales.£35.00m2016
University BuildingManchesterDay to day QS duties including the preparation of Final Account for agreement with Client and agreement of Sub-Contractor accounts£8.60m2012
Secondary SchoolNorth WarwickshirePreparation of Final Account for specialist Sub-Contractor including claim for loss and or expense due to prolongation of the Works£4.90m2011
Primary SchoolSalfordPreparation of Final Account for specialist Sub-Contractor£320k2011
SEN SchoolBuryPreparation of report into various design issues predominantly involving M&E Services and the resultant effect both financially & in relation to delay and disruption to the Works2011
Secondary SchoolTamesidePreparation of Final Account for specialist Sub-Contractor including claim for loss and or expense due to prolongation of the Works£3.80m2010
CollegeCheshirePre-Construction Manager of a 2nd stage tender of a College New Build and Refurbishment project valued at approximately £11m
This role included agreeing the scope of works with the client and design team followed by the preparation of the relevant procurement documentation and the tendering process
£11.00m2010
CollegeCheshireBid Manager of £10m College Scheme£10.00m2008
CollegeCheshireValue Engineering of a new college£23.00m2007
CollegeLancashireExtension of Time requests£13.50m2007
Secondary SchoolManchesterProcurement of work package£21.50m2007
CollegeManchesterGeneral Day to Day QS duties£5.00m2007
Secondary SchoolRuncornGeneral Day to Day QS duties£2.60m2007
University BuildingPrestonRegional Commercial Manager£8.00m2005
School extensionLeedsRegional Commercial Manager£8.00m2004
Secondary SchoolLeedsRegional Commercial Manager
New school extension & Sports Hall
£7.80m2004
School extensionLeedsRegional Commercial Manager
3 projects at different schools for same local authority under design and build contracts
£4.00m2003

Commercial

SectorLocationResponsibilitiesValueYear
Office BuildingLiverpoolEngaged by Main Contractor to undertake Account Review on selected Sub-Contract packages to determine potential financial liability on £8m Design and Build Office development in Liverpool.£8.00m2016
Office Fit OutManchesterFinal Accounts & Claim preparation
including several successful adjudications
£12.75m2008
Office & MSCPHullRegional Commercial Manager£6.50m2004
Great NorthernManchesterCommercial Manager overseeing team of up to 5 QSs£45.00m2001
St John's Shopping CentreLiverpoolManaging QS Preparation of Final Account
including claim for loss and or expense due to prolongation of the Works
£5.50m1999
Retail ParkCheadleDay to day QS duties£3.00m1992
Office & MSCPSalford QuaysDay to day QS duties£25.00m1991

Accommodation

SectorLocationResponsibilitiesValueYear
ApartmentsManchesterEngaged by Main Contractor to provide Contractual advice on 135 bed apartment £21m project in Manchester in respect of delays to progress and instructed changes to the Works, including preparation of the Claim for Loss and Expense.£21.00m2016
Student AccommodationManchesterJCT2011 Design and Build Contract [Sub-Contract Work Package only]
Contractual advice to Consultant engaged by the MEP Contractor in respect of an Application for Loss and or Expense following the Main Contractor going into administration
£4.90m2015
Student AccommodationNottinghamBid Manager on design and build tender to convert existing Office development into 140 bed Student Accommodation including steel frame extension.£4.20m2011
ApartmentsWiganSubcontract Final Accounts2008
ApartmentsLiverpoolSubcontract Final Accounts2008
HousingNorthwestRegional Commercial Manager.
Responsible for approximately 18 projects at any one time including new build and refurbishment
£65.00m2006

Healthcare

SectorLocationResponsibilitiesValueYear
Primary CareCheshireRegional Commercial Manager£6.00m2006
Primary CareMerseysideRegional Commercial Manager£7.00m2005
Clinical SciencesManchesterRegional Commercial Manager£6.50m2004
Pathology LabBoltonDay to day QS duties£3.00m1996
Hospital extensionsStockportDay to day QS duties£7.70m1994

Retail

SectorLocationResponsibilitiesValueYear
Retail Fit-OutManchesterDay to day Quantity Surveying duties including the preparation and agreement of Sub-Contractor accounts and preparation of Final Account documentation to the Employer£30.00m2012 - 2013
Retail Fit-OutManchesterReview of submitted £13.00m final account to determine the technical and contractual position on the project and prepare report on same2011
Airport RetailManchesterDay to day QS duties£6.50m1996

Hotels

SectorLocationResponsibilitiesValueYear
Hotel DevelopmentDerbyPreparation of Final Account for specialist Sub-Contractor including claim for loss and or expense due to prolongation of the Works£5.30m2010

Leisure

SectorLocationResponsibilitiesValueYear
GalleryManchesterPreparation of multiple, Relevant Matters including Extension of Time requests and development of Position Statements in respect of matters in dispute.

Working closely with engaged Forensic Planner to prepare extensive report to evidence an entitlement to a 49 week extension of time together with the resultant substantial claim for Loss and Expense
£23.00m2013 - 2015
Football StadiumLancashirePreparation of Final Account for specialist Sub-Contractor including claim for loss and or expense due to prolongation of the Works£1.70m2011
Swimming PoolCo DurhamRegional Commercial Manager£7.00m2004
Holiday ParkNorth YorkshireRegional Commercial Manager£5.30m2003

Industrial

SectorLocationResponsibilitiesValueYear
Hi-bay WarehouseWiganBid management of 2nd Stage process£18.00m2000
WarehouseHaydockManaging QS including the preparation of Final Account£3.00m1997

Engineering

SectorLocationResponsibilitiesValueYear
Factory & OfficesStaffordshireProviding contractual and commercial advice on the implications of a Deed of Agreement and revised Sectional Completion Dates and to review what, if any opportunities may be apparent in respect of the programme to completion and the current commercial status of the project.
Advise on technical issue regarding work installed but appearing to fail.
Advise on the MEP account and received request for an Extension of Time and resultant Loss and Expense claim documentation.
£18.00m2015
Factory & OfficesStaffordshireCompliance Review 'Health Check' to ensure entitlement for extensions of time and applications for loss and expense are being applied for in accordance with the Contract.£18.00m2014
Motor FacilityStaffordshireBid Manager on tender to design and build new Motor Facility for Client involved in the defence industry.£1.90m2011
MetrolinkManchesterPreparation of Final Account for specialist Sub-Contractor including claim for loss and or expense due to prolongation of the Works£2.60m2011

Local Authority

SectorLocationResponsibilitiesValueYear
Retail Refurbishment & New BuildHalifaxRestoration of the existing buildings together with various new build extensions and the construction of a new building to house a central library and archive£25.00m2017
Town Hall RefurbishmentBoltonNWCH PSPC Option 6 Contract - Contractor Design Target Cost with Cost Reimbursable
Review of extension of time requests and preparation of final documentation to allow agreement of the overall account
£12.80m2015
Care HomeBarrowNWCH PSPC Option 6 Contract - Target Cost with Cost Reimbursable with Contractor Design.
Contractual advice to Consultant engaged by the MEP Contractor in respect of an Application for Loss and or Expense following the Main Contractor going into administration
£1.20m2015